Contractor guide · Change orders

How to write a change order as a contractor

A change order is a written, approved change to the scope, price or schedule of a job you already agreed on. Below: what goes on one, how to price it, how to get a quick yes, what to do when the customer says no, a worked example, and a template to copy. General information, not legal advice.

Short answer

Write down what changes and why, the price of the change, the new total, any extra days, and how the change gets paid. Point it at the original quote. Get the customer’s signature or written approval before you do the extra work, and keep it with the job.

Last updated:

On this page
  1. 01What a change order is
  2. 02When you need one
  3. 03What goes on it
  4. 04How to price it
  5. 05Getting it approved
  6. 06If the customer says no
  7. 07A worked example
  8. 08Template to copy
  9. 09State rules
  10. 10Where LeadHunter USA fits

What a change order is

Your quote or contract sets the scope and the price. When either one moves after the customer said yes, the change order is the paper that records the new deal. The original quote still stands, and the job’s final price is the original total plus or minus every approved change order.

If you are still writing the first price, start with how to write a contractor estimate. The difference between an estimate, a quote and an invoice is in estimate vs quote vs invoice vs receipt.

When you need one

  • The customer adds or changes the work. A second outlet, a bigger patio, a different tile layout.
  • You find hidden damage. Rot under the floor, a corroded pipe inside the wall, wiring that has to be brought up before you can close it.
  • The customer upgrades a material. A selection above the allowance on the quote, or a different model than the one you priced.
  • Something comes out of the job. The customer supplies a fixture, or drops a room. That is a change order too, with a credit.

Small changes add up. The fifteen-minute extra that you do for free on day two is the one the customer remembers as included when the final bill arrives. Write it down even when the price is zero.

What goes on a change order

Eight things. Most fit on one page, and many fit on a phone screen.

  1. 01

    Change order number and date. Number them in order: Change order 1, 2, 3. The date is the day you wrote it.

  2. 02

    The original quote or contract. Its number and date, and the job address, so nobody wonders which job this belongs to.

  3. 03

    What is changing. What you will add, remove or do differently, in plain words. Say why: the customer asked, or you found something you could not see before.

  4. 04

    The price of the change. Labor and materials as separate lines. A credit for work removed is a minus line.

  5. 05

    The new total. Original price, plus or minus every change order so far, equals the new contract price.

  6. 06

    Time impact. How many days the change adds, or “no change to the finish date”. Say it even when it is zero.

  7. 07

    How the change is paid. Due on approval, or added to the next payment or the final payment. One sentence.

  8. 08

    Approval. The customer’s signature or typed name, your signature, and the date, before you do the work.

Put your business name and license number on it the same way they appear on your quote, so the change order clearly belongs to the same contract.

How to price a change order

Price it the way you priced the original job, with the same labor rate and the same markup, so the customer can see it follows the quote they already accepted. If you need to check your markup math, the markup vs margin calculator is on the estimate guide.

LineWhat to countEasy to miss
LaborHours for the extra work, at the rate you used on the original quoteInclude setup, cleanup and the return trip if the change needs one
MaterialsWhat you buy for the change, with your usual markupKeep the receipt with the job
CreditWork or materials taken out of the jobSubtract what that work was worth on the original quote
Time on the scheduleExtra days you are tied up on this jobA day here can be a day you can’t book elsewhere

For hidden damage you can’t fully see yet, give a fixed price for the part you can see, and write how anything beyond it will be priced (for example, by the hour at your quoted rate, up to a limit the customer approves). That keeps the customer from signing an open check.

If you ask for money up front on the change, the same deposit rules as the original job may apply in your state. See how much deposit a contractor can take.

How to present it so the customer approves

  • Tell them first, then send the paper. Show the problem in person or by photo, explain the fix in a sentence, and say the change order is coming.
  • Send it the same day. A change order written while the wall is open gets approved faster than one sent a week later.
  • Give a choice when there is one. A full fix and a smaller fix, each with its price, lets the customer decide instead of feeling cornered.
  • Show the new total. Customers worry most about where the total ends up. Put it in bold under the change.
  • Make approving easy. One action: sign, type their name, or tap approve. Then start the work.

Set this up before the job starts. Put one line on every quote saying changes are priced and approved in writing first. The paste-ready wording is in the scope and exclusions block of the estimate guide.

What to do if the customer refuses

  • Do not do the extra work. Doing it anyway is how a change turns into an unpaid bill.
  • Ask what part they object to: the price, the need, or the timing. Often a smaller fix or a later date solves it.
  • If the change is about hidden damage, explain in writing what leaving it means for your work and your warranty on that part.
  • If they still decline, write a short note that they were offered the change and said no, with the date, and keep it with the job.
  • Finish the original scope and invoice it as agreed.

If the dispute ends up being about money already owed, the steps are in customer won’t pay your invoice.

A worked example

Made up for this page. The names, the job and the prices are examples only. Sales tax is left out to keep the math simple.

Example job

A contractor has an approved quote (Quote 1042) for a bathroom remodel for a homeowner we will call Sam Example. The quote total is $8,400. On day two, the old tub comes out and the subfloor under it is soft. Sam also says they bought their own vanity light, so the contractor doesn’t need to supply one.

The contractor stops, shows Sam a photo of the subfloor, and sends Change order 1 that afternoon:

  • Remove and replace about 15 sq ft of subfloor under the tub. Labor, 4 hours: +$340
  • Subfloor panels, screws and adhesive: +$120
  • Vanity light supplied by the customer (contractor installs it): −$90
  • Net change: +$370. New total: $8,770.
  • Time: adds 1 day. New finish date moves from Friday to Monday.
  • Payment: the $370 is added to the final payment.

Sam approves it that evening. The contractor replaces the subfloor the next morning, and the final invoice shows Quote 1042, Change order 1 as its own line, the deposit already paid, and the balance.

Change order template to copy

Plain text, so it pastes into a text message, an email, or the notes of any document. Fill in the blanks.

Change order template

CHANGE ORDER #____ · Date: ____

Business: ____ · License #: ____ · Phone: ____

Customer: ____ · Job address: ____

Original quote/contract: #____, dated ____, total $____

Change: ____ (what will be added, removed or done differently)

Reason: ____ (requested by customer / found during work: ____)

Price of this change: Labor $____ · Materials $____ · Credit −$____ · Net change +/− $____

Contract total: Original $____ + previous change orders $____ + this change $____ = New total $____

Schedule: Adds ____ days / No change to the finish date. New finish date: ____

Payment for this change: Due on approval / Added to the next payment / Added to the final payment

All other terms of the original quote/contract stay the same. Work on this change starts only after this change order is approved.

Customer signature: ________ Date: ____

Contractor signature: ________ Date: ____

Prefer a filled-in document instead of plain text? The free estimate and invoice maker builds one you can download.

State rules on change orders

Rules differ by state, and some states set out what a home improvement contract and its changes must include. Check your state’s contractor board. One example we read, from California’s state license board:

“If the contract price or scope of work needs to be changed, it MUST be done with a written ‘Change Order,’ signed by the customer and contractor prior to the change, which then becomes a part of the contract.”

Source: California Contractors State License Board, What is a home improvement contract, read 6 November 2026

We don’t describe states we haven’t read. General information, not legal advice.

Where LeadHunter USA fits

LeadHunter USA CRM has no separate change-order form. Here is how a change works with what it does have:

  • Before the customer approves, edit the quote. A quote you already sent becomes a new version at the same link.
  • After approval, the quote is locked. Make a new quote for the same customer that covers only the change. It can have two or three options (a full fix and a smaller one), a deposit, and a valid-until date.
  • The customer opens the link on their phone and approves by typing their name, or taps “Ask a question / Request changes”. You can also collect the approval in person on your own device.
  • With LeadHunter USA Payments on (optional, 3.3% + 30¢ per US card), the customer can pay the change’s deposit by card from the approved quote.
  • “Create invoice from quote” is always your click and makes a draft invoice. Each quote gets its own invoice, and a draft can still be edited before you send it.
  • Under the terms, “Add common wording” includes a sample line saying changes are priced and approved in writing before the extra work.

Good fit

  • Solo and small contractors who want the change priced and approved on the customer’s phone
  • Contractors who already send quotes from the free CRM and want the change on the same customer’s card

Not the right tool

  • Anyone who needs a document titled “Change order”: in LeadHunter USA CRM a change is a new quote
  • Crews where a project manager or office approves changes: there are no team logins

Create your free account What LeadHunter USA CRM does

From LeadHunter USA LLC

Price the change and get it approved from the customer’s phone

Quotes with options and deposits, approval from a link, and invoices made from approved quotes, in the free LeadHunter USA CRM.

Create your free account
  • LeadHunter USA CRM

    Send quotes and invoices, and keep every customer and job in one place.

    Free

  • LeadHunter USA Payments

    Customers pay you by card: show a QR code on the spot or send a pay link. Works on its own or with the CRM. Stripe sends the money to your bank: the first payout takes about 7–14 days from your first card payment, then about 2 business days.

    Free to join · 3.3% + 30¢ per US card

  • LeadHunter USA Alerts

    People nearby asking for your trade, sent to your phone within minutes, while your computer is on.

    7 days free, then $75/month

  • LeadHunter USA Line Pro

    Your personal assistant on every call. After a call, tap Yes: it writes the call out, fills in the customer’s card, puts the visit on your calendar, drafts the quote or invoice from what you said, and reminds you if you agreed to talk later. You check it and tap Send. Nothing goes to a customer without you.

    $39 first month, then $89/mo

LeadHunter USA Alerts is the paid lead-alert product; the CRM does not need it. Payments works on its own or with the CRM.

Questions

Common questions

What is a change order in construction?

A change order is a short written agreement that changes the scope, price or schedule of a job that was already agreed. It names the original quote or contract, describes the change, gives the price difference and the new total, states any change to the finish date, and is approved by the customer before the extra work is done.

What should a contractor change order include?

A change order number and date; the original quote or contract number and the job address; a description of the change and why; the price of the change, with credits as minus lines; the new total; the time impact; how the change will be paid; and the customer’s and contractor’s signatures with the date.

Can I do extra work first and write the change order later?

It is a common source of unpaid bills. Without a written approval before the work, the customer can say they never agreed to the price. In California, the state license board says a change to the price or scope of a home improvement contract must be done with a written change order signed by both before the change. Other states have their own rules; check your state’s contractor board.

Does a change order have to be signed?

Get it signed or approved in writing every time, whatever your state requires. A text that says “approved” is better than nothing; a signed or typed-name approval on the change order itself is clearer, because it is tied to the exact description and price.

Can a change order lower the price?

Yes. When the customer takes something out of the job, or supplies a material themselves, write the change as a credit (a minus line) and show the lower new total.

What if the customer won’t approve the change order?

Do not do the extra work. Stop at the point where the change matters, explain in writing what the hidden problem means for the job, and offer choices: approve the change, pick a smaller fix, or leave that part as it is with a written note that they declined.