Contractor guide · Getting paid

Contractor payment schedule: deposit, progress and final payments

A payment schedule says how much the customer pays, and when, from the deposit to the final payment. Below: the common structures by job size, how to tie payments to finished work, three worked examples and a schedule you can paste into a quote. The first payment is limited by state law in some states, so check your state’s deposit limit first.

Short answer

Small jobs: a deposit when the customer approves, the rest on completion. Multi-day jobs and remodels: a deposit, then progress payments tied to finished stages, then a final payment at the walkthrough. Write each payment in dollars, with what makes it due, on the quote before work starts. Keep the deposit inside your state’s limit.

Last updated:

On this page
  1. 01Payment structures by job size
  2. 02Your state’s deposit limit
  3. 03Milestones, not dates
  4. 04Worked examples
  5. 05Writing it into the quote
  6. 06A schedule you can paste
  7. 07When a payment is late
  8. 08Where LeadHunter USA fits

Payment structures by job size

The bigger and longer the job, the more payments it usually takes, so that neither side carries too much of the money at once. Three common shapes:

JobStructureHow the money comes in
Small job, done in a day or twoDeposit and final, or payment on completionA deposit when the customer approves (or none), the rest when the work is done
Multi-day jobDeposit, one or two progress payments, finalEach progress payment is due when a named stage is finished
Larger remodelDeposit, several milestone payments, finalOne payment per finished stage, with the final held for the walkthrough

Retainage, briefly. Some contracts hold back a share of each payment until the end of the job. You’ll mostly see it on commercial work and jobs for general contractors. If a contract you sign has retainage, write down how much is held and what releases it.

Start with your state’s deposit limit

The deposit is the one payment several states limit directly. We read the home improvement statutes of all 50 states and DC: 9 cap the deposit, 14 more attach a deadline, an escrow or trust rule, or a condition, and in the other 28 we found no statewide limit. Each state’s rule, linked to its statute, with a calculator, is on how much deposit a contractor can take.

General information, not legal advice. A city or county can add its own rules, and most state rules have exceptions for bonds, special-order materials or types of work. Read the section for your state before you set your terms.

Tie progress payments to finished work, not dates

A progress payment works when both of you can see that its stage is done. Dates and percentages invite arguments: the date arrives whether or not the work did, and “half done” means something different to each side.

Milestones anyone can check

  • Cabinets delivered to the site
  • Rough plumbing and electrical inspection passed
  • Drywall hung and taped
  • Tile set and grouted
  • Final walkthrough done and punch list finished

Milestones that cause arguments

  • “Week 2” or “the 15th”
  • “50% complete”
  • “When framing is mostly done”
  • Anything only your word can confirm

Keep each payment close to the value of the work done and materials delivered so far. A schedule that runs ahead of the work asks the customer to trust you with money for work that isn’t there yet. One that runs far behind means you are paying for the job yourself.

Some state rules reach past the deposit. From our state list: California limits a home improvement down payment to $1,000 or 10% of the contract, whichever is less; later payments may not run ahead of the work done. Read your own state’s entry on the deposit limits page.

Worked examples

Made-up round numbers to show the shape of each schedule. Your prices and stages will differ. In every example the payments add up to the contract price.

Small job, done in a day: a water heater replacement: $1,800

One visit, materials bought the same week. Two payments are enough.

PaymentDue whenAmountBalance after
DepositWhen the customer approves the quote$300$1,500
FinalWhen the new heater is installed and running$1,500$0

Multi-day job: a bathroom remodel: $9,000

About two weeks of work with an inspection in the middle. Each payment follows a stage the customer can see.

PaymentDue whenAmountBalance after
DepositWhen the customer approves the quote$1,000$8,000
Progress 1Demolition done and rough plumbing inspection passed$3,500$4,500
Progress 2Tile set and fixtures installed$3,000$1,500
FinalFinal walkthrough done and punch list finished$1,500$0

Larger remodel: a kitchen: $24,000

Several weeks, large material orders, more than one inspection. More milestones keep each payment close to the work done.

PaymentDue whenAmountBalance after
DepositWhen the customer approves the quote$2,000$22,000
Progress 1Cabinets and appliances delivered to the site$6,000$16,000
Progress 2Rough plumbing and electrical inspection passed$5,000$11,000
Progress 3Cabinets and countertops installed$6,000$5,000
FinalFinal walkthrough done and punch list finished$5,000$0

Check the deposit against your state. In a state with a cap, the deposit in these examples may need to be smaller. In California, for one, the deposit on the $9,000 bathroom job works out to at most $900. The deposit calculator works it out for your state and total.

How to write the schedule into the quote

  • Start with the total contract price, then list each payment under it.
  • Give each payment a dollar amount, the stage that makes it due, and how many days after that stage it is due.
  • If you think in percentages, write the dollars too, and check that the payments add up to the total.
  • Tie the final payment to completion and a walkthrough, not to “when you’re happy”.
  • Say how change orders affect the schedule: a change order adds a payment or changes one, in writing.
  • Say how the customer can pay, and when a payment counts as late.

The schedule is one part of the estimate. The rest (scope, exclusions, license number, sales at the home) is in how to write a contractor estimate. Showing each payment received on the bill is in how to invoice as a contractor. Whether the whole agreement has to be in writing in your state, and from what amount, is in home improvement contract requirements by state.

A payment schedule you can paste

Fill in the blanks and paste it into the terms of your quote. Keep the deposit inside your state’s limit, and add any wording your state requires.

Payment schedule

Payment schedule

Total contract price: $____

1. Deposit: $____, due when you approve this quote. It reserves your start date of ____ and pays for ordering ____.

2. Progress payment: $____, due within __ days after ____ is complete.

3. Progress payment: $____, due within __ days after ____ is complete.

4. Final payment: $____, due within __ days after the work is complete and we have walked through it together.

When a stage is complete, we will send you a photo of it and the amount due.

Changes to the work or price are written as a change order, approved by you, and may add or change a payment above.

If a payment is more than __ days late, work may pause until it is paid. We will tell you in writing first.

You can pay by: ____.

What to do when a milestone payment is late

  1. Ask on the day. When the stage is done, send a short text with a photo and the amount from the schedule. A request made while the finished work is in front of the customer is easy to act on.
  2. Remind in writing. After the due date in your schedule, send a polite reminder. Wording for each step is in payment-reminder texts.
  3. Hold the next cost. Wait to order the next stage’s materials until the late payment comes in, so the amount at risk stops growing.
  4. Pause only if the agreement says so. If your schedule says work may pause on a late payment, tell the customer in writing, with the date work stops and what restarts it. Without that term, stopping can turn into a dispute about who broke the agreement.
  5. If it stays unpaid. Send a final notice, then choose between small claims court, a lien where your state has one, or a write-off. The steps are in customer won’t pay your invoice. Lien rules are state law, and some start with a notice early in the job, so check yours before the work begins.

A late fee belongs on the quote the customer approved, within your state’s limits. Adding one later, on the invoice only, is easy to dispute.

Where LeadHunter USA fits

LeadHunter USA CRM is free. A quote can carry a deposit, as a dollar amount or a percent of the total, and the customer sees it as due on approval. They approve from a link on their phone, or in person on your device. With card payments on, they can pay the deposit by card through LeadHunter USA Payments: 3.3% + 30¢ per US card, to your own Stripe account. For home-improvement trades, the quote builder can show the job-site state’s deposit rule under the totals, from the same list as the deposit limits page. It is a hint and never blocks sending.

Each quote has its own terms, so the schedule above can go there, or into your saved default terms. When the job starts, turn the approved quote into its invoice: the deposit already received is counted on it. Record each progress payment as it comes in. The customer’s invoice link shows every payment with its date and how it was paid, and the balance left, and a partly paid invoice can get a reminder sent from your own phone.

What it does not do: there is one invoice per quote, with no separate progress invoices, and the invoice’s card button charges the whole remaining balance, not one milestone. Card fees and payout timing are in how to accept card payments as a contractor.

Good fit

  • Solo contractors and small crews who quote, invoice and get paid from a phone
  • Jobs with a deposit and one or a few payments after it
  • Customers who pay by card, check, cash, Zelle or Venmo

Not the right tool

  • Jobs billed with a separate invoice for each progress payment
  • Contracts with retainage held back until the end
  • Bank (ACH) payments or a card reader

Create your free account What LeadHunter USA CRM does

From LeadHunter USA LLC

Take the deposit on approval, then track every payment

Put your payment schedule in the terms of a quote in the free LeadHunter USA CRM. The customer approves it on their phone and can pay the deposit by card: 3.3% + 30¢ per US card, to your own Stripe account. The invoice counts the deposit, and each payment you record shows on it with its date.

Create your free account
  • LeadHunter USA CRM

    Send quotes and invoices, and keep every customer and job in one place.

    Free

  • LeadHunter USA Payments

    Customers pay you by card: show a QR code on the spot or send a pay link. Works on its own or with the CRM. Stripe sends the money to your bank: the first payout takes about 7–14 days from your first card payment, then about 2 business days.

    Free to join · 3.3% + 30¢ per US card

  • LeadHunter USA Alerts

    People nearby asking for your trade, sent to your phone within minutes, while your computer is on.

    7 days free, then $75/month

  • LeadHunter USA Line Pro

    Your personal assistant on every call. After a call, tap Yes: it writes the call out, fills in the customer’s card, puts the visit on your calendar, drafts the quote or invoice from what you said, and reminds you if you agreed to talk later. You check it and tap Send. Nothing goes to a customer without you.

    $39 first month, then $89/mo

LeadHunter USA Alerts is the paid lead-alert product; the CRM does not need it. Payments works on its own or with the CRM.

Questions

Common questions

What is a contractor payment schedule?

A written list of when the customer pays: the deposit, any progress payments and the final payment, each with a dollar amount and the event that makes it due. It goes on the quote or contract before the work starts, and the amounts add up to the contract price.

How much can a contractor ask for up front?

It depends on the state and the job. Of the 50 states and DC, 9 cap the deposit on home improvement work and 14 more attach a deadline, an escrow or trust rule, or a condition. In the other 28 we found no statewide limit in the statutes we read. Check your state on our deposit limits page before you set the first payment. General information, not legal advice.

Should progress payments be tied to dates or to finished work?

To finished work. A milestone such as “rough plumbing inspection passed” is something both sides can check. A date keeps arriving even when the job is behind, which leaves the customer paying ahead of the work, or you arguing about whether a payment is due.

What should I do when a progress payment is late?

Ask for it the day the milestone is reached, with a photo of the finished stage. Remind in writing after the due date. Hold off on ordering the next stage’s materials. Pause work only if your written agreement says work may pause on a late payment, and tell the customer in writing first. If it stays unpaid, follow the steps for an unpaid invoice.

Can I stop work if the customer misses a payment?

Put it in the agreement first. If your schedule says work may pause when a payment is a set number of days late, give the customer written notice with the date work stops and what restarts it. Without that term, stopping can turn into a dispute about who broke the agreement. State rules on contracts and liens vary. General information, not legal advice.

What is retainage?

A share of each payment held back until the job is finished, then paid at the end. It shows up mostly on commercial jobs and work for general contractors. If a contract you sign has it, write down how much is held and what releases it.

Can LeadHunter USA CRM split one invoice into progress payments?

It keeps one invoice per quote. The deposit paid on the quote is counted on that invoice, you record each later payment on it as it comes in, and the customer’s link lists every payment with its date and the balance left. It has no separate progress invoices, and the invoice’s card button charges the whole remaining balance.